Project Status
Inside and outside side putty work completed on 30.09.2024





Outer Plastering work completed on 31.03.2024




Brick work and inside plastering completed on Date- 30/12/2023



6th Slab Completed: 25/05/2023




5th Slab Completed: 25/04/2023



4th Slab Completed: 05/01/2023




3rd Slab Completed: 15th Nov 2022




2nd Slab Completed: 18th Oct 2022